Jan 02 at 11:10am GMT
–
Jan 02 at 04:10pm GMT
Affected services
ms3networks.co.uk
Resolved
Jan 02 at 11:10am GMT
MS3 are performing emergency maintenance, to replace equipment in the HU8 area.
Date and time (from and to) of Change:
02.01.2025 - 11:10 - 16:10
Description of the work:
FAT - 1-8 splitter replacement to improve the quality and stability of the MS3 network.
FDT - 1-4 splitter replacement to improve the quality and stability of the MS3 network
TRACE AND TEST - Testing an incoming fibre further back in the network to trace a fault.
Customers located in HU8 may experience up to 5 HRS interruption to their service, however we will endeavour to minimise the outage where possible and may complete the improvement activity ahead of schedule.