Maintenance
Planned Maintenance
Jun 28 at 09:00am BST
–
Jun 28 at 05:00pm BST
Affected services
ms3networks.co.uk
Resolved
Jun 28 at 09:00am BST
MS3 are performing planned maintenance activity on Friday 28th June.
Date and time of Change:
Friday 28th June from 09:00 until 17:00
Description of the work:
New carrier pole installed, 3 new spans to existing customers, taking cable to the CTU, and cut old cable off and splice new cable, recommissioning required by NOC while Ops remove old equipment.
Expected Impact:
Customer impact expected later in the day, ETA 15:00 for not more than an hour (time it takes for recommission to take place)
Affected services
ms3networks.co.uk